Project Information 1

Common Core Management LSU. The following Work in Progress report shows two medical projects in progress. Complete the report by calculating the missing values (a,b,c,d,e,f,g, and h) and answer the following multiple-choice questions.

Work in Progress Report Data:

Job DescriptionRevised Contract Amount (B)Revised Estimated Costs (D)Billed to Date (H)Cost to Date (I)
Sierra MOB21,978,70020,803,00416,576,44915,270,450
VA Hospital876,615,150843,952,138338,285,590311,198,009

Question 1

What is the missing value of (b)?

  • a. 65.5%
  • b. 73.41%
  • c. 71.29%
  • d. 55.74%
  • e. 58.24%

Question 2

What is the missing value of (c)?

  • A. 15,550,350
  • B. 16,133,470
  • C. 11,271,450
  • D. 13,552,450
  • E. 16,367,500

Question 3

What is the missing value of (d)?

  • A. over 650,000
  • B. Over 442,979
  • C. over 1,305,999
  • D. under 567,000
  • E. under 2,305,999

Question 4

What is the missing value of (f)?

  • A. 31.23%
  • B. 36.87%
  • C. 52.32%
  • D. 67.45%
  • E. 23.62%

Question 5

What is the missing value of (g)?

  • A. 352,568,707
  • B. 392,598,000
  • C. 323,242,133
  • D. 235,290,129
  • E. 107,198,009

Question 6

What is the missing value of (h)?

  • A. under 15,055,236
  • B. under 16,055,016
  • C. over 11,575,267
  • D. over 25,087,581
  • E. over 15,043,457

Project Information 2

The roll-up schedule below outlines a maintenance project. After 6 weeks on the project, the actual cost to date is 42,716.00. Based on a review of the project, activities A, B, and C are 100% complete. Additionally, activities D and E are 50% complete, and activity F is 20% complete. No other activities or work have started. Complete the four multiple-choice questions for a project status report.

Activity Data Table:

  • Activity A: Duration 1 wk, Budgeted Cost 2,500
  • Activity B: Duration 2 wks, Budgeted Cost 6,700
  • Activity C: Duration 7 wks, Budgeted Cost 7,000
  • Activity D: Duration 3 wks, Budgeted Cost 15,600
  • Activity E: Duration 2 wks, Budgeted Cost 11,000
  • Activity F: Duration 5 wks, Budgeted Cost 25,000
  • Activity G: Duration 2 wks, Budgeted Cost 25,000
  • Activity H: Duration 4 wks, Budgeted Cost 12,000
  • Activity I: Duration 2 wks, Budgeted Cost 10,500
  • Activity J: Duration 6 wks, Budgeted Cost 5,300
  • Activity K: Duration 1 wk, Budgeted Cost 2,500

Question 7

What is the budgeted cost of work and the earned value of the project?

  • A. BCWS = 40,800.00 BCWP = EV = 42,400.00
  • B. BCWS = 40,800.00 BCWP = EV = 34,500.00
  • C. BCWS = 41,800.00 BCWP = EV = 42,000.00
  • D. BCWS = 39,500.00 BCWP = EV = 42,500.00
  • E. BCWS = 40,500.00 BCWP = EV = 34,500.00

Question 8

Calculate the schedule variance and percent schedule variance.

  • A. SV = +2,500 % SV = +5.35 %
  • B. SV = +1,950 % SV = +5.30 %
  • C. SV = +2,154 % SV = +5.39 %
  • D. SV = -6,300 % SV = -15.44 %
  • E. SV = -6,300 % SV = -12.32 %

Question 9

Calculate the cost variance and percent cost variance.

  • A. CV = -8,216 % CV = -23.81%
  • B. CV = +8,216 % CV = +23.85%
  • C. CV = -1,160 % CV = -2.85%
  • D. CV = -1,290 % CV = -2.74%
  • E. CV = +7,822 % CV = +22.74%

Question 10

Calculate the percent complete and planned percent complete?

  • a. PC = 26.03 % PPC = 32.14 %
  • b. PC = 21.21% PPC = 27.0 %
  • c. PC = 32.23 % PPC = 37.12%
  • d. PC = 26.21 % PPC = 35.44 %
  • e. PC = 28.03 % PPC = 33.14 %

Question 11

Calculate the estimate at completion.

  • A. 142,512.65
  • B. 152,415.62
  • C. 148,655.23
  • D. 160,254.32
  • E. 155,214.36

Question 12

Calculate the estimate to complete.

  • A. 109,699.62
  • B. 110,542.36
  • C. 105,423.65
  • D. 108,235.14
  • E. 112,412.36

Question 13

Calculate the variance at completion.

  • A. Over budget by 19,412.36
  • B. Over budget by 29,315.62
  • C. Under budget by 25,412.36
  • D. Over budget by 32,145.23
  • E. Under budget by 20,123.65

Question 14

Calculate the to-complete performance index.

  • A. 1.0521
  • B. 1.1542
  • C. 1.1022
  • D. 1.0823
  • E. 1.1214

Question 30

Daily logs should be completed each day during construction and should record any conditions that affect the work on that particular day

  • True
  • False

Answer: True


Question 31

6- The difference between current assets and current liabilities is called equity

  • True
  • False

Answer: False (It is called Working Capital)


Question 32

7- When using random sampling, if the number of samples is reduced to save on costs, the statistical tests may result in accepting unsatisfactory units

  • True
  • False

Answer: True


Question 33

8- Retainage is the amount of money that a contractor charges the Owner for overhead and profit

  • True
  • False

Answer: False (It is money withheld to ensure project completion)


Question 34

9- An environmental impact statement (EIS) is an example of a submittal that a contractor submits to the owner and architect for review during construction

  • True
  • False

Answer: False (It is a regulatory document typically handled during planning)


Question 35

10- Design-build is a type of delivery method that combines the constructor and designer into one entity

  • True
  • False

Answer: True


Question 36

11- A statistical t-test is used for quality control to determine if two sets of samples have the same mean

  • True
  • False

Answer: True


Question 37

12- Real estate is a long-term liability

  • True
  • False

Answer: False (It is a fixed asset)


Question 38

13- Construction companies in the U.S. typically use the GAAP accounting system

  • True
  • False

Answer: True


Question 39

14- IPD is a common delivery method used for very large, publicly-funded infrastructure projects

  • True
  • False

Answer: False (Procurement laws usually require traditional bidding)


Question 40

  1. This step in the value methodology is when the VE team calculates the value index.
  • A. Audit
  • B. Evaluation
  • C. Implementation
  • D. Pre-study
  • E. Function analysis review

Answer: B. Evaluation


Question 41

  1. Of the following management activities, which one addresses defining the desired project objectives?
  • A. Scoping
  • B. Controlling
  • C. Planning
  • D. Managing
  • E. Organizing

Answer: C. Planning


Question 42

  1. This document shows a company’s source of income, production costs, and other expenses for a given period of time.
  • A. Income statement
  • B. Work in progress report
  • C. Balance Sheet
  • D. Earned value analysis
  • E. Cash Flow statement

Answer: A. Income statement


Question 43

  1. Which of the following is a type of quality control?
  • A. Program management
  • B. Poor design
  • C. Appreciation
  • D. Insurance
  • E. Submittals

Answer: E. Submittals

AIA Payment Application Summary

The following questions are based on the AIA Document G702 (Application and Certification for Payment) and G703 (Continuation Sheet). These documents are used to track the financial progress of a construction project.

  • AIA G702: Provides a summary of the contract sum, changes, total completed to date, retainage, and the current amount due.
  • AIA G703: Breaks down the contract into specific line items (e.g., Masonry, Roofing, Mechanical), showing the scheduled value and the work completed for each.

Key formulas used in these calculations include:

  • Total Completed and Stored to Date: Previous Application+This Period+Materials Stored
  • Total Earned Less Retainage: Total Completed & Stored−Total Retainage
  • Current Payment Due: Total Earned Less Retainage−Previous Certificates

Question 15

What is the missing value of (A)?

  • A. $1,586,119.88
  • B. $1,386,219.88
  • C. $1,754,119.45
  • D. $1,656,251.00
  • E. $1,865,191.50

Question 16

What is the missing value of (B)?

  • A. $125,911.00
  • B. $155,911.99
  • C. $135,850.99
  • D. $163,754.99
  • E. $145,921.50

Question 17

What is the missing value of (C)?

  • A. $163,251.99
  • B. $157,261.99
  • C. $155,160.45
  • D. $157,221.75
  • E. $175,261.99

Question 18

What is the missing value of (D)?

  • A. $1,428,857.89
  • B. $1,482,558.89
  • C. $1,548,325.89
  • D. $1,284,657.99
  • E. $1,582,857.85

Question 19

What is the missing value of (E)?

  • A. $662,861.58
  • B. $635,881.58
  • C. $625,861.45
  • D. $662,681.85
  • E. $665,800.50

Question 20

What is the missing value of (F)?

  • A. $1,039,032.11
  • B. $1,035,321.11
  • C. $1,253,032.11
  • D. $1,149,032.21
  • E. $1,930,222.21

Question 21

What is the current payment due?

  • A. $661,110.00
  • B. $954,458.78
  • C. $604,661.10
  • D. $662,861.58
  • E. $1,586,119.88

Question 22

What is the missing value of (H)?

  • A. $148,456.00
  • B. $32,455.00
  • C. $175,150.00
  • D. $163,251.00
  • E. $180,911.00

Question 23

What is the missing value of (I)?

  • A. $35,215.00
  • B. $17,450.00
  • C. $55,235.00
  • D. $64,763.00
  • E. $24,567.00

Question 24

What is the missing value of (J)?

  • A. 72.77%
  • B. 73.64%
  • C. 75.25%
  • D. 70.12%
  • E. 78.44%

Question 25

What is the missing value of (J) [for the Roofing row]?

  • A. $14,999.00
  • B. $15,900.00
  • C. $19,300.00
  • D. $10,500.00
  • E. $5,400.00

Question 26

What is the missing value of (K)?

  • A. $149.90
  • B. $1,065.00
  • C. $1,590.00
  • D. $1,499.90
  • E. $1,930.00

Question 27

What is the missing value of (M)?

  • A. $1,559,119.88
  • B. $1,586,119.88
  • C. $954,458.78
  • D. $604,661.10
  • E. $2,704,041.00

Question 28

What is the missing value of (N)?

  • A. $1,144,921.12
  • B. $1,250,921.12
  • C. $1,111,921.12
  • D. $1,117,110.12
  • E. $1,117,921.12

Facebook
WhatsApp
Twitter
LinkedIn
Pinterest

Leave a Comment

Recent posts
Follow us on
× Chat Now